There’s been a lot going on at the brewery over the last few weeks. All of the walls are up with the exception of the fire exit corridor, which should be complete by the middle of this coming week.


With drywall applied to one side of each wall, the plumbers and electricians are finishing up their installations which will be inspected before the walls are sealed up.

Every once in a while we get a break in the weather! Here Rohry is working on taking down the rotten old “side wings” on the front overhang. Fortunately the central overhang is in good shape.

New grain crusher

New grain case

Keg washer, beer pump, and temperature controls

2 Replies to “Progress Report and New Equipment”

    1. We’re just waiting for final approval from the Comptroller’s office. Apparently everything is fine with our application… there’s just some processing time. We will post as soon as we know what’s going on and we will open VERY shortly thereafter!